Saturday, May 18

Construction Corner


Thursday, March 13, 1997

The Department of Water and Power water main relocation project
is in progress. Fencing has been erected across the Intramural (IM)
Field extending out to Bruin Walk, blocking all pedestrian traffic
on Bruin Walk from the west end of the John Wooden Center to the
Bruin Bear. Pedestrians are detoured between the J.D. Morgan Center
and James West Alumni Center. The water main relocation is part of
the Parking Structure Four expansion project.

Construction continues on the interior of Young Hall. Contractor
trailers are situated in the Shlichter Hall courtyard.

Workers are reinstalling spires atop the Kerckhoff Hall tower,
with interior remodel work underway. Exterior scaffolding is in
place.

There is some telecommunications work being done in a manhole on
Circle Drive South at the Cogen Plant. Facilities management
continues to build a new clubhouse at the women’s softball field on
Bellagio Drive.

Trench work continues at the site of the Brain Mapping building.
Traffic is limited to one lane in each direction.

At the Bradley International Student Center, construction
continues. Trucks entering and leaving the site cause minor traffic
congestion on Circle Drive near Strathmore.

Construction continues at the Gonda (Goldschmied) Neuroscience
and Genetics Research Center, causing minor traffic congestion
resulting from steel deliveries.

Compiled by Toni Dimayuga, Daily Bruin Contributor.


Comments are supposed to create a forum for thoughtful, respectful community discussion. Please be nice. View our full comments policy here.